Updated 13 November 2026. Compiled by the Dholera Atlas desk from the sources listed at the end of this page.
Bloomberg reported on 17 July 2026 that the Tata Electronics fab at Dholera will run mostly on 90nm at the start. Tata replied that it will offer 28nm to 110nm, that the plan has always been to start with 55nm and 90nm, and that 28nm will follow and be a key part of the offering. No date for 28nm has been given. Commercial operations are guided for mid-2028. Checked 13 November 2026.
Technology node claims for the Dholera fab, in date order
| Date | Who said it | What it says about the node | How firm it is |
|---|---|---|---|
| 29 February 2024 | Union Cabinet release (PIB), with the Tata Electronics release of the same day | Fab with partner PSMC, 50,000 wafer starts a month, Rs 91,000 crore. The segments listed are high performance compute chips with 28 nm technology and power management chips | Approval, capacity and investment are firm; the release names 28 nm as the technology for compute chips and gives no start order for nodes |
| 23 July 2026 | Business Standard, citing Tata Electronics | Designed for 28nm, 40nm, 55nm, 90nm and 110nm; production was always meant to begin with 55nm and 90nm before 28nm is added | Company statement, reported |
| 17 July 2026 | Bloomberg, as summarised by TrendForce on 20 July 2026 | Production is expected to rely mainly on 90nm at launch, not 28nm | Report with sources not named in our summary |
| 20 July 2026 | Tata Electronics spokesperson, quoted by TrendForce | Nodes from 28nm to 110nm; the plan has always been to start with 55nm and 90nm, then add 28nm | Company statement |
| 20 July 2026 | PSMC spokesperson, quoted by TrendForce | The partnership covers multiple nodes with 28nm the most advanced, and technology transfers come in gradually | Partner statement |
| 20 July 2026 | Technology Minister Ashwini Vaishnaw, as reported by TrendForce | Commercial operations expected in mid-2028 | Ministerial statement, reported |
| Undated, 2026 | Broker and property sites | A December 2026 production start | Not supported by the reports above; treat as out of date |
Download this table (CSV). Last checked 13 November 2026. Free to quote with a link to this page.
What a technology node is
A technology node, written in nanometres, is a label for a manufacturing generation. A smaller number generally means smaller transistors and more of them on a chip, but the number is a naming convention and not a measured length. 28nm is more advanced than 55nm or 90nm. All three are called mature nodes, which means they are widely used and cost less per wafer than the leading edge. Our page on process nodes explained covers the idea in full.
What the 2024 approval said about 28nm
The Union Cabinet release of 29 February 2024 describes the fab as covering high performance compute chips with 28 nm technology and power management chips for vehicles, telecom, defence, display and power electronics. It gives the capacity as 50,000 wafer starts a month and the investment as Rs 91,000 crore, and it names PSMC as technology partner. It does not say which node would be produced first. That gap is why the July 2026 reports read as a change to many people, even though the company says its start order was always 55nm and 90nm. Business Standard on 23 July 2026 also recorded that the group chairman had earlier pointed to 28nm as the starting point of its semiconductor journey, which is a statement about direction and not a production schedule.
Why 90nm at the start is not a contradiction
The two sides of the July 2026 story fit together more closely than the headline suggests. Tata did not say 28nm would open first. Its spokesperson said the plan was always to start with 55nm and 90nm, then bring in 28nm. Bloomberg's point is that the first volume will be mostly 90nm. The disagreement is about emphasis and timing, not about which nodes exist in the plan. Neither source gives a date for 28nm.
What kinds of chips run on 28 to 110nm
Mature nodes make power chips, display drivers, microcontrollers and many automotive and industrial parts. Our page on power and analog chips explains why these products do not need the newest process. A fab on these nodes is not a rival to the most advanced foundries in Taiwan, and the owners have not described it as one.
What is firm and what is not
Firm: the Cabinet approved the project on 29 February 2024, PSMC is the technology partner, and the design capacity is up to 50,000 wafer starts a month. Reported: the 90nm emphasis at launch, the 28nm to 110nm range and the mid-2028 timing. Not stated in any source we hold: the date 28nm production starts, the share of each node, and the first customer volumes. A Digitimes report of 12 October 2026 says Tata has six customers at different engagement stages, three of them reportedly with binding commitments, but its source is anonymous and we treat it as unconfirmed.
What would settle the question
- A technology transfer milestone announced by Tata Electronics or PSMC.
- A tool-install or first-silicon announcement naming the node.
- A Ministry of Electronics and IT or India Semiconductor Mission release with the commercial operations date.
- Customer announcements that name the process.
Until one of these appears, the node question stays open in the sense that only the starting emphasis has been reported.
A line only this atlas can add
Our ranked list of Indian fabs and OSAT units by approved investment places this project first by size, and the Dholera fab page on this site, the Tata fab at Dholera, carries the capacity and investment figures with their sources. The older text there that mentions a December 2026 first-silicon target is not backed by later reporting.
Questions people ask
Will the Tata Dholera fab make 28nm chips?
Tata says its range spans 28nm to 110nm and that 28nm will be a key part of the offering. The same statement says the plan was always to start with 55nm and 90nm first. No start date for 28nm has been given, as of 13 November 2026.
Is the Dholera fab 90nm or 28nm?
Both appear in the plan. Bloomberg reported on 17 July 2026 that output will be mainly 90nm at launch. Tata says 55nm and 90nm come first and 28nm follows. A single starting node has not been announced by the company.
When will the Tata Dholera fab start production?
Technology Minister Ashwini Vaishnaw is reported to have said commercial operations are expected in mid-2028, as per TrendForce on 20 July 2026. An earlier target of end 2026 has been moved. Broker claims of December 2026 production are not supported.
What is the capacity of the Tata Dholera fab?
The design capacity is up to 50,000 wafer starts a month, with an investment of about Rs 91,000 crore, per the Cabinet release of 29 February 2024. These are design and approval figures, not production output.
Who is PSMC and what does it do at Dholera?
Powerchip Semiconductor Manufacturing Corporation is a Taiwanese foundry and Tata Electronics' technology partner. A PSMC spokesperson said the partnership covers multiple nodes, with 28nm the most advanced, and that technology transfers are typically introduced gradually.
Is 90nm outdated?
No. It is a mature node used widely for power, display and microcontroller chips. It is less advanced than 28nm but costs less and serves many products that do not need small transistors. The choice is about the product mix, not about being behind.
Read next
- The Tata fab at Dholera
- Process nodes explained
- Power and analog chips
- Indian fabs and OSAT units ranked by investment
- Dholera master plan map
Sources
- Tata's India fab reportedly to launch at 90nm instead of 28nm, TrendForce citing Bloomberg (20 July 2026)
- Business Standard: Not cutting-edge, but can Tata's chip fab reduce India's import bill? (23 July 2026)
- PIB: Giant leap for India Semiconductor Mission, Cabinet approves three more semiconductor units (29 February 2024)
- Tata Electronics press release: Tata Group to build the nation's first fab in Dholera (29 February 2024)
- PIB: Fiscal Support Agreement for the Dholera fab, 50 per cent central support (March 2025)
- Digitimes report on Tata Electronics customers (paywalled) (12 October 2026)