Of the 12 semiconductor manufacturing projects approved under the India Semiconductor Mission, with about Rs 1.64 lakh crore in total, the Tata Electronics fab at Dholera is the largest at about Rs 91,000 crore, more than half of the total. Tata's Assam packaging unit (Rs 27,000 crore) and Micron's Sanand plant (Rs 22,516 crore) follow. A second Dholera unit, Crystal Matrix, is reported at Rs 3,068 crore.

How this list is rankedRanked on one fact: the investment amount stated at Cabinet approval for each project under the India Semiconductor Mission. Figures come from the Cabinet approvals of 2023 to May 2026 (Press Information Bureau releases, which blocked our automated fetch on 11 November 2026) as reported by Business Standard, Business Today, The Week, Tribune, Deccan Herald and IANS, and each figure was confirmed in at least two reports. The Cabinet gave one combined figure of Rs 3,936 crore for Crystal Matrix (Dholera) and Suchi Semicon (Surat); the split of Rs 3,068 crore and Rs 868 crore is as reported by Indian newsrooms. The Tata fab is stated at about Rs 91,000 crore in the Cabinet release; Business Today (August 2026) gives Rs 91,526 crore. All figures are approved investment, not money spent.

Approved projects by investment

RankProjectLocationTypeApproved investmentIn Dholera?
1Tata Electronics with PSMCDholera, GujaratSilicon fabRs 91,000 croreYes
2Tata Semiconductor Assembly and TestMorigaon, AssamPackaging and testRs 27,000 croreNo
3Micron TechnologySanand, GujaratAssembly and test (DRAM, NAND)Rs 22,516 croreNo
4CG Power with Renesas and StarsSanand, GujaratAssembly and testAbout Rs 7,600 croreNo
5HCL and Foxconn joint ventureJewar, Uttar PradeshDisplay driver chipsRs 3,706 croreNo
6Kaynes SemiconSanand, GujaratAssembly and testRs 3,307 croreNo
7Crystal MatrixDholera, GujaratCompound semiconductor (gallium nitride) and Mini/Micro-LED modulesRs 3,068 crore (reported split of a combined Rs 3,936 crore)Yes
8SiCSemBhubaneswar, OdishaSilicon carbide compound semiconductorsRs 2,066 croreNo
93D Glass SolutionsBhubaneswar, OdishaAdvanced packaging, glass substratesRs 1,943 croreNo
10Suchi SemiconSurat, GujaratAssembly and test (discrete devices)Rs 868 crore (reported split of a combined Rs 3,936 crore)No
11ASIP TechnologiesAndhra PradeshPackagingRs 468 croreNo
12CDIL (Continental Device India)Mohali, PunjabPower semiconductor devicesRs 117 croreNo

Dholera's share

The listed figures add to about Rs 1,63,652 crore, in line with the government's stated Rs 1.64 lakh crore. The Tata fab alone is about Rs 91,000 crore, about 56% of that. Adding Crystal Matrix, the other Dholera project, at Rs 3,068 crore, the two Dholera projects hold about 57% of approved investment. Crystal Matrix's separate figure is reported, not stated in the Cabinet release.

Note the difference between three kinds of unit. A fab makes the chip on a silicon wafer. An assembly and test unit (OSAT) packs and tests cut chips. Compound semiconductor units make chips from materials other than silicon. By one measure, the Tata fab is the only silicon fab on the list.

Status is not the same as approval

Approval means the Union Cabinet cleared the project. It does not say whether a unit is built or running, and this page does not print a production status for any project. The Tata fab at Dholera is under construction.

Why a ranking by money can mislead

A larger amount does not mean a larger number of chips or workers. A fab costs far more per unit of output than a packaging line. Compare units of the same type when you compare projects.

What this list cannot tell you

This list shows approved investment under one national scheme. It excludes projects outside the scheme and cannot show spending, output or dates.

Questions people ask

How many semiconductor projects are approved in India?

Twelve manufacturing projects, with about Rs 1.64 lakh crore, under the India Semiconductor Mission as of mid-2026: one silicon fab, two compound semiconductor units and nine packaging units, per a June 2026 report.

Which is India's biggest semiconductor project?

The Tata Electronics and PSMC fab at Dholera, at about Rs 91,000 crore approved investment, with capacity up to 50,000 wafers a month.

Is Micron's plant in Dholera?

No. Micron's assembly and test plant is in Sanand, Gujarat.

What is an OSAT unit?

An outsourced semiconductor assembly and test unit. It takes finished chips from a fab, packages them in a casing and tests them.

Read next

Sources

  1. IANS, India approves 12 chip manufacturing projects with Rs 1.64 lakh crore (28 June 2026)
  2. Business Standard, Cabinet approves Kaynes Rs 3,307 crore unit (2 September 2024)
  3. Business Today, Cabinet clears two new semiconductor units in Dholera and Surat (5 May 2026)
  4. Tribune, Govt clears 4 chip plants in Punjab, Andhra, Odisha at cost of Rs 4,594 crore (12 August 2025)
  5. Deccan Herald, Union Cabinet approves Rs 3,706 crore semiconductor unit in Uttar Pradesh (14 May 2025)
  6. The Week, Centre approves three semiconductor units (Tata fab, Tata Assam, CG Power) (29 February 2024)
  7. PIB, Cabinet approvals under the India Semiconductor Mission (not fetchable on 11 November 2026) (2023 to May 2026)