India's approved semiconductor projects ranked by investment, with Dholera's place
Updated 11 November 2026. Compiled by the Dholera Atlas desk from the sources listed at the end of this page.
Of the 12 semiconductor manufacturing projects approved under the India Semiconductor Mission, with about Rs 1.64 lakh crore in total, the Tata Electronics fab at Dholera is the largest at about Rs 91,000 crore, more than half of the total. Tata's Assam packaging unit (Rs 27,000 crore) and Micron's Sanand plant (Rs 22,516 crore) follow. A second Dholera unit, Crystal Matrix, is reported at Rs 3,068 crore.
Approved projects by investment
| Rank | Project | Location | Type | Approved investment | In Dholera? |
|---|---|---|---|---|---|
| 1 | Tata Electronics with PSMC | Dholera, Gujarat | Silicon fab | Rs 91,000 crore | Yes |
| 2 | Tata Semiconductor Assembly and Test | Morigaon, Assam | Packaging and test | Rs 27,000 crore | No |
| 3 | Micron Technology | Sanand, Gujarat | Assembly and test (DRAM, NAND) | Rs 22,516 crore | No |
| 4 | CG Power with Renesas and Stars | Sanand, Gujarat | Assembly and test | About Rs 7,600 crore | No |
| 5 | HCL and Foxconn joint venture | Jewar, Uttar Pradesh | Display driver chips | Rs 3,706 crore | No |
| 6 | Kaynes Semicon | Sanand, Gujarat | Assembly and test | Rs 3,307 crore | No |
| 7 | Crystal Matrix | Dholera, Gujarat | Compound semiconductor (gallium nitride) and Mini/Micro-LED modules | Rs 3,068 crore (reported split of a combined Rs 3,936 crore) | Yes |
| 8 | SiCSem | Bhubaneswar, Odisha | Silicon carbide compound semiconductors | Rs 2,066 crore | No |
| 9 | 3D Glass Solutions | Bhubaneswar, Odisha | Advanced packaging, glass substrates | Rs 1,943 crore | No |
| 10 | Suchi Semicon | Surat, Gujarat | Assembly and test (discrete devices) | Rs 868 crore (reported split of a combined Rs 3,936 crore) | No |
| 11 | ASIP Technologies | Andhra Pradesh | Packaging | Rs 468 crore | No |
| 12 | CDIL (Continental Device India) | Mohali, Punjab | Power semiconductor devices | Rs 117 crore | No |
Dholera's share
The listed figures add to about Rs 1,63,652 crore, in line with the government's stated Rs 1.64 lakh crore. The Tata fab alone is about Rs 91,000 crore, about 56% of that. Adding Crystal Matrix, the other Dholera project, at Rs 3,068 crore, the two Dholera projects hold about 57% of approved investment. Crystal Matrix's separate figure is reported, not stated in the Cabinet release.
Note the difference between three kinds of unit. A fab makes the chip on a silicon wafer. An assembly and test unit (OSAT) packs and tests cut chips. Compound semiconductor units make chips from materials other than silicon. By one measure, the Tata fab is the only silicon fab on the list.
Status is not the same as approval
Approval means the Union Cabinet cleared the project. It does not say whether a unit is built or running, and this page does not print a production status for any project. The Tata fab at Dholera is under construction.
Why a ranking by money can mislead
A larger amount does not mean a larger number of chips or workers. A fab costs far more per unit of output than a packaging line. Compare units of the same type when you compare projects.
What this list cannot tell you
This list shows approved investment under one national scheme. It excludes projects outside the scheme and cannot show spending, output or dates.
Questions people ask
How many semiconductor projects are approved in India?
Twelve manufacturing projects, with about Rs 1.64 lakh crore, under the India Semiconductor Mission as of mid-2026: one silicon fab, two compound semiconductor units and nine packaging units, per a June 2026 report.
Which is India's biggest semiconductor project?
The Tata Electronics and PSMC fab at Dholera, at about Rs 91,000 crore approved investment, with capacity up to 50,000 wafers a month.
Is Micron's plant in Dholera?
No. Micron's assembly and test plant is in Sanand, Gujarat.
What is an OSAT unit?
An outsourced semiconductor assembly and test unit. It takes finished chips from a fab, packages them in a casing and tests them.
Read next
Sources
- IANS, India approves 12 chip manufacturing projects with Rs 1.64 lakh crore (28 June 2026)
- Business Standard, Cabinet approves Kaynes Rs 3,307 crore unit (2 September 2024)
- Business Today, Cabinet clears two new semiconductor units in Dholera and Surat (5 May 2026)
- Tribune, Govt clears 4 chip plants in Punjab, Andhra, Odisha at cost of Rs 4,594 crore (12 August 2025)
- Deccan Herald, Union Cabinet approves Rs 3,706 crore semiconductor unit in Uttar Pradesh (14 May 2025)
- The Week, Centre approves three semiconductor units (Tata fab, Tata Assam, CG Power) (29 February 2024)
- PIB, Cabinet approvals under the India Semiconductor Mission (not fetchable on 11 November 2026) (2023 to May 2026)