What is already built in Dholera, and what is not yet open
Updated 11 November 2026. Compiled by the Dholera Atlas desk from the sources listed at the end of this page.
Built or in service in Dholera as of 11 November 2026: the 109 km Ahmedabad-Dholera Expressway (inaugurated 31 March 2026, reported), about 300 MW of solar, the Activation Area's water, power and effluent networks, the ABCD command building and a 3,200 m airport runway that took a trial landing on 4 June 2026. The airport itself is not open.
Built and in service, with status
| Order | What exists | Detail | Status (11 Nov 2026) | Source and date |
|---|---|---|---|---|
| 1 | Ahmedabad-Dholera Expressway | 109 km, four lanes, access-controlled, expandable to eight; NHAI | Inaugurated 31 March 2026 (reported) | Press reports, March 2026; NHAI |
| 2 | Dholera solar park, first phase | About 300 MW commissioned of 1,000 MW sanctioned for Phase I; the long-range target is 5,000 MW | Operating; remaining 700 MW in development | NICDC DMU report, 30 June 2026; CEA quarterly report, September 2025 |
| 3 | Activation Area trunk utilities | Water treatment plant, three 66 kV substations, 115 km underground power duct, effluent plant, recycled water and ICT ducts | Reported built | DSIRDA Sanctioned Development Plan; DICDL interview, 2024 |
| 4 | ABCD building and command centre | Administrative and business centre housing the Integrated Command and Control Centre | Reported operational; opening date not stated | DICDL, as recorded in July 2026 |
| 5 | Internal roads in the Activation Area | About 72 km, 18 to 70 metres wide | Reported built | DICDL interview, 2024 |
| 6 | Airport runway, taxiways and control tower | 3,200 m runway near Pipli village; first trial landing by an Airports Authority of India aircraft on 4 June 2026 | Built; airport not open | Gujarat Samachar and trade press, June 2026; CM review, 16 October 2026 |
The airport: runway built, airport not open
The runway landing proves the runway can be used. It does not make Dholera International Airport operational. As of 11 November 2026 no aerodrome licence from the aviation regulator and no airline schedule has been reported. The Airports Authority of India signed an operation and management agreement with the airport company on about 4 November 2026. Officials told the Chief Minister on 16 October 2026 that the airport is expected to be operational by the end of 2026. The passenger terminal was reported about 75% complete in July 2026, and we hold no newer percentage.
Solar: what 300 MW means
The NICDC Delivery Monitoring Unit report of 30 June 2026 records 300 MW of the 1,000 MW sanctioned for the first phase. Tata Power describes its own 300 MW Dholera plant as using India's largest single-axis tracker. The record does not reconcile whether these two are the same 300 MW, so we state one figure: about 300 MW in service.
How to see it yourself
- The expressway can be driven from Ahmedabad. Travel times in reports vary from about 40 minutes to an hour, so measure it yourself.
- The Activation Area and ABCD building are visible from the public roads in Dholera, but access to utility sites and construction areas is controlled.
- Ask DICDL for a site visit if you are an investor.
What this list cannot tell you
This list shows what sources say is built. It cannot show how much of a built item is used, whether its capacity is free, or what happens next to it.
Questions people ask
What has been built in Dholera so far?
The expressway (inaugurated 31 March 2026, reported), about 300 MW of solar, Activation Area utilities and roads, the ABCD command building and an airport runway with a trial landing on 4 June 2026. Reported by official and newsroom sources.
Is Dholera airport open?
No. As of 11 November 2026 it is not open. Officials expect operation by the end of 2026. No licence or airline schedule has been reported.
Is the Ahmedabad-Dholera expressway open?
Reported inaugurated on 31 March 2026. Toll rates for cars were not found in the sources we checked, so none is stated here.
Is anything built in the smart city, or is it only a plan?
Utilities, roads, a command centre and a solar park are reported built. Larger items such as the Tata fab, the terminal and the rail line are under construction or planned.
Read next
Sources
- NICDC Delivery Monitoring Unit report (30 June 2026)
- DSIRDA and DICDL, Dholera SIR (extracted July 2026)
- NewKerala, Chief Minister's review of Dholera works (16 October 2026)
- Indian Masterminds, AAI and DIACL agreement (3 November 2026)