Dholera Atlas

What is already built in Dholera, and what is not yet open

Updated 11 November 2026. Compiled by the Dholera Atlas desk from the sources listed at the end of this page.

Built or in service in Dholera as of 11 November 2026: the 109 km Ahmedabad-Dholera Expressway (inaugurated 31 March 2026, reported), about 300 MW of solar, the Activation Area's water, power and effluent networks, the ABCD command building and a 3,200 m airport runway that took a trial landing on 4 June 2026. The airport itself is not open.

How this list is rankedEntries are things that official or major-newsroom sources describe as built, commissioned or in service. Under-construction works (the Tata fab, the terminal, the rail line) are in a separate list on this site. Order runs from what a visitor can use today to what exists but is not open. Each row says what kind of source states it. We have not inspected the sites.

Built and in service, with status

OrderWhat existsDetailStatus (11 Nov 2026)Source and date
1Ahmedabad-Dholera Expressway109 km, four lanes, access-controlled, expandable to eight; NHAIInaugurated 31 March 2026 (reported)Press reports, March 2026; NHAI
2Dholera solar park, first phaseAbout 300 MW commissioned of 1,000 MW sanctioned for Phase I; the long-range target is 5,000 MWOperating; remaining 700 MW in developmentNICDC DMU report, 30 June 2026; CEA quarterly report, September 2025
3Activation Area trunk utilitiesWater treatment plant, three 66 kV substations, 115 km underground power duct, effluent plant, recycled water and ICT ductsReported builtDSIRDA Sanctioned Development Plan; DICDL interview, 2024
4ABCD building and command centreAdministrative and business centre housing the Integrated Command and Control CentreReported operational; opening date not statedDICDL, as recorded in July 2026
5Internal roads in the Activation AreaAbout 72 km, 18 to 70 metres wideReported builtDICDL interview, 2024
6Airport runway, taxiways and control tower3,200 m runway near Pipli village; first trial landing by an Airports Authority of India aircraft on 4 June 2026Built; airport not openGujarat Samachar and trade press, June 2026; CM review, 16 October 2026

The airport: runway built, airport not open

The runway landing proves the runway can be used. It does not make Dholera International Airport operational. As of 11 November 2026 no aerodrome licence from the aviation regulator and no airline schedule has been reported. The Airports Authority of India signed an operation and management agreement with the airport company on about 4 November 2026. Officials told the Chief Minister on 16 October 2026 that the airport is expected to be operational by the end of 2026. The passenger terminal was reported about 75% complete in July 2026, and we hold no newer percentage.

Solar: what 300 MW means

The NICDC Delivery Monitoring Unit report of 30 June 2026 records 300 MW of the 1,000 MW sanctioned for the first phase. Tata Power describes its own 300 MW Dholera plant as using India's largest single-axis tracker. The record does not reconcile whether these two are the same 300 MW, so we state one figure: about 300 MW in service.

How to see it yourself

  • The expressway can be driven from Ahmedabad. Travel times in reports vary from about 40 minutes to an hour, so measure it yourself.
  • The Activation Area and ABCD building are visible from the public roads in Dholera, but access to utility sites and construction areas is controlled.
  • Ask DICDL for a site visit if you are an investor.

What this list cannot tell you

This list shows what sources say is built. It cannot show how much of a built item is used, whether its capacity is free, or what happens next to it.

Questions people ask

What has been built in Dholera so far?

The expressway (inaugurated 31 March 2026, reported), about 300 MW of solar, Activation Area utilities and roads, the ABCD command building and an airport runway with a trial landing on 4 June 2026. Reported by official and newsroom sources.

Is Dholera airport open?

No. As of 11 November 2026 it is not open. Officials expect operation by the end of 2026. No licence or airline schedule has been reported.

Is the Ahmedabad-Dholera expressway open?

Reported inaugurated on 31 March 2026. Toll rates for cars were not found in the sources we checked, so none is stated here.

Is anything built in the smart city, or is it only a plan?

Utilities, roads, a command centre and a solar park are reported built. Larger items such as the Tata fab, the terminal and the rail line are under construction or planned.

Read next

Sources

  1. NICDC Delivery Monitoring Unit report (30 June 2026)
  2. DSIRDA and DICDL, Dholera SIR (extracted July 2026)
  3. NewKerala, Chief Minister's review of Dholera works (16 October 2026)
  4. Indian Masterminds, AAI and DIACL agreement (3 November 2026)