What is still on the plan in Dholera, with the latest target for each
Updated 11 November 2026. Compiled by the Dholera Atlas desk from the sources listed at the end of this page.
The nearest targets are the airport (expected operational by the end of 2026, after Sept to Oct 2026) and the remaining 700 MW of solar (March 2027). The Tata fab is reported for commercial production around mid-2028, the L&T Vyoma data centre and Embraer plan for about 2028 (reports differ for the data centre), and the semi high-speed rail for 2030 to 2031. Targets move; each row shows the date stated.
Planned works by latest target
| Order | Work | Latest target | Earlier target | Status (11 Nov 2026) | Source and date |
|---|---|---|---|---|---|
| 1 | Dholera International Airport operations | End of 2026 | Sept to Oct 2026 (ministry, July 2026); December 2025 target missed | Not open; trial landing 4 June 2026; AAI operation agreement about 4 November 2026 | Chief Minister's review, 16 October 2026; AIR, 14 July 2026 |
| 2 | Solar park Phase I, remaining 700 MW | March 2027 | Not stated | In development; awards to Tata Power, Vena, ReNew, SJVN and TEQ Green; delayed by tariff disputes | CEA quarterly report, September 2025 |
| 3 | DHL semiconductor logistics warehouse | About August 2027 | None stated | Reported plan of about Rs 50 crore | Electronics For You, 15 October 2026 |
| 4 | Tata fab, commercial production | Around mid-2028 | Commercial production by the end of 2026 was reported earlier (Inc42, 13 March 2024) | Under construction; no source confirms a chip made | Minister Vaishnaw, 15 July 2026, reported by TrendForce citing Bloomberg, 20 July 2026 |
| 5 | L&T Vyoma data centre, 250 MW | About 2028 (reports differ: operational by 2028, or proposed start of development) | None stated | MoU, feasibility stage | newsonair.gov.in, 20 February 2026 |
| 6 | Embraer civil aircraft assembly at Dholera airport | Around 2028 | None stated | Memorandum signed January 2026; Dholera reported as the site in June 2026, not confirmed by the companies; no amount stated | PTI report via PSU Watch, June 2026; ANI, 31 March 2026 |
| 7 | Ahmedabad to Dholera semi high-speed rail, 134 km, Rs 20,667 crore | Up to 2030 to 2031 | None stated | Cabinet approved 13 May 2026; no construction start reported | PIB release 2260624, 13 May 2026 |
| 8 | Bhimnath to Dholera 23 km logistics line | Not stated | Approved by the NICDIT board on 21 September 2021 | Being developed; no date reported | NICDC DMU report; CM review, 16 October 2026 |
Why targets are shown with the earlier date
The airport target moved from December 2025 to September and October 2026 and then to the end of 2026. The fab's commercial production moved to about mid-2028. Showing both dates lets a reader see the pattern for themselves. It is a record, not a judgement.
What is not on this list
Hospital, school, guest house and hotel works reported by local portals are left out because we found them only at local-portal level, apart from a Chief Minister's review on 16 October 2026 that mentions several as under way. Water works (a 2,200 million litre raw water reservoir and desalination plans) are announced or at planning stage with no operating date.
A note on the fab's chip size
Bloomberg reported in July 2026 that the fab will launch mostly on 90 nm chips. Tata says it will span 28 to 110 nm. A claim of December 2026 production appears on broker pages and conflicts with the reported mid-2028 target.
What this list cannot tell you
This list shows stated targets. It cannot predict whether a date will hold, and it does not imply any change in land value.
Questions people ask
When will Dholera airport open?
Officials said on 16 October 2026 that it is expected to be operational by the end of 2026. It is not open as of 11 November 2026, and no licence or airline schedule has been reported. Earlier targets were missed.
When will the Tata fab in Dholera start production?
Minister Ashwini Vaishnaw said on 15 July 2026 that commercial operations are expected around mid-2028, as reported by TrendForce citing Bloomberg on 20 July 2026. An earlier report in March 2024 expected first chips by the end of 2026. No source we hold confirms a chip has been made.
When will the Ahmedabad Dholera rail be ready?
The Cabinet approved a 134 km semi high-speed line on 13 May 2026 with completion targeted up to 2030 to 2031. No construction start has been reported.
Why do Dholera targets keep changing?
Large works depend on clearances, contracts and weather. The airport and the fab both have moved targets on record. Always use the date and source rather than a round number.
Read next
Sources
- PIB, Cabinet approval of the Ahmedabad-Dholera semi high-speed rail (13 May 2026)
- newsonair.gov.in, Dholera airport to become operational in three months (14 July 2026)
- NewKerala, Chief Minister's review (16 October 2026)
- CEA quarterly report on solar parks (September 2025)
- TrendForce, Bloomberg report on the Tata fab node and mid-2028 timeline (20 July 2026)
- PSU Watch, Adani Group and Embraer finalise Dholera for aircraft assembly line (June 2026)